Payment Schedule


1. Initial Booking Amount : 15%
2. Upon execution of Agreement : 10%
3. After Completion of Foundation : 25%
4. After Completion of Roof Slab of respective Floor : 15%
5. After completion of Brick work of respective flat : 15%
6. After completion of Plastering of respective Flat : 10%
7. After completion of Flooring of respective Flat : 5%
8. On or before Possession : 5%